← Go back to Testing Farm Status

BaseOS CI limited due to outage due to BRQ network maintanance.

November 12, 2023 at 12:00 AM UTC

BaseOS CI

Resolved after 36h 0m November 13, 2023 at 12:00 PM UTC

Resolved 12:00 UTC - Registry is back, outage is resolved. The tests should automatically resume, no manual intervention should be needed.

Outage 00:00 UTC - Our BRQ image registry went down after BRQ network maintanance. This is blocking BaseOS CI autoscaling, so the queue can get large. We are working to resolve the issue.

Last updated: August 5, 2024 at 11:34 AM UTC